ANALISIS BIAYA PADA PROYEK URUGAN LIMESTONE RESTORASI DI BIBIR PANTAI NEW GRASS ROOT REFINERY KILANG MINYAK TUBAN

Authors

  • Sugiyanto Program Studi Teknik Sipil Fakultas Teknik, Universitas Sunan Bonang, Tuban, Jawa Timur, Indonesia
  • Joni Setiyono Program Studi Teknik Sipil Fakultas Teknik, Universitas Sunan Bonang, Tuban, Jawa Timur, Indonesia

DOI:

https://doi.org/10.22225/pd.11.2.5311.199-206

Keywords:

control, cost, performance, schedule

Abstract

In the implementation of construction projects, cost control is one of the most important targets in achieving cost performance status. This study aim to of analyze the cost of the restoration limestone backfill project on the shoreline of the new grass root refinery of the Tuban oil refinery. The data used were obtained from PT. Wira Karya Tehnika as the project contractor who has a budget of IDR 1,596,270,000.00 and a duration of 90 days whereby a planned implementation schedule is from November 19, 2021 to February 16, 2022. The earned value method is used in analyzing data which consists of variables, indicators and index earned value. The results of the analysis obtain a pattern formed on the 3 earned value variables at an integrated curve in the duration of the 1st to 13th week of the project, achieving cost performance status on budget. Furthermore, the analysis results of the cost variance provide very strong certainty that the cost performance of the analyzed project implementation can be controlled very well. Finally, the results of the analysis of the cost performance index is an undeniable fact that the project costs can be controlled very well.

References

Barrie, D. S., Paulson, B., & Sudinarto. (1990). Manajemen Konstruksi Profesional (Edisi 2). Jakarta: Erlangga.

Dipohusodo, I. (1996). Manajemen Proyek Dan Konstruksi. Jakarta: Kanisius.

Ervianto, W. I. (2015). Teori-Aplikasi Manajemen Proyek Konstruksi (Ed. Revisi). Jogjakarta: Andi Offset.

Husen, A. (2011). Manajemen Proyek. Jogjakarta: Andi Offset.

Mabin, V., & Balderstone, S. (1998). A Review of Goldratt’s Theory of Constraints-Lessons from the International Literature. Operational Research Society of New Zealand 33rd Annual Conference, Auckland.

Mandiyo, P. (2021). Earned Value Management System in Indonesian Construction Projects. International Journal of Integrated Engineering, 13(3), 37–45.

Pastiarsa, M. (2015). Manajemen Proyek Konstruksi Bangunan Industri: Perspektif Pemilik Proyek. Yogjakarta: Teknosain.

PT Wira Karya Tehnika. (2022a). Bill Off Quantity Proyek Pekerjaan Restorasi Garis Pantai Untuk Pembangunan Kilang Dan Fasilitas Terminal Untuk Kepentingan Sendiri (TUKS) Di Tuban. Kontrak Konstrukai RBB 045-095422 Ditanda Tangani Antara PT Wira Karya Teknika Dengan PT Putra Badak Arun Solusi (Member of Pertamina Indonesia).

PT Wira Karya Tehnika. (2022b). Laporan Intensitas Kemajuan Proyek Periode Mingguan Proyek Pekerjaan Restorasi Garis Pantai Untuk Pembangunan Kilang Dan Fasilitas Terminal Untuk Kepentingan Sendiri (TUKS) Di Tuban. Kontrak Konstrukai RBB 045-095422 Ditanda Tangani Antara PT Wira Karya Teknika Dengan PT Putra Badak Arun Solusi (Member of Pertamina Indonesia).

Rani, H. (2016). Manajemen Proyek Konstruksi. Yogjakarta: Deepublish.

Soeharto, I. (2019). Manajemen Proyek Dari Konseptual Sampai Operasional. Jakarta: Erlangga.

Sugiyanto. (2020). Manajemen Pengendalian Proyek. Surabaya: Scopindo Media Pustaka.

Sugiyanto, A., & Gondokusumo, O. (2020). Perbandingan Metode Earned Value, Earned Schedule, Dan Kalman Filter Earned Value Untuk Prediksi Durasi Proyek. JMTS: Jurnal Mitra Teknik Sipil, 3(1), 155–166. https://doi.org/10.24912/jmts.v3i1.7069

Sugiyanto, & Kosbiamtoro, A. (2021). Cost Performance Analysis of the Drainage and Sidewalk Rehabilitation Project of Jalan Teuku Umar Package I with Earned Value Method. International Journal of Inovation and Engineering Science Research, 5(5), 72–84.

Sugiyanto, & Kosbiamtoro, A. (2022). Analisis Kinerja Biaya Pada Proyek Rehabilitasi Drainase Dan Trotoar Jalan Teuku Umar Paket I Dengan Metode Earned Value. Jurnal Litbang Sukowati, 5(2), 126–141. https://doi.org/10.32630/sukowati.v5i2.320

Sugiyanto, & Untoko, R. (2022). Evaluasi Sistem Manajemen Pada Pelaksanaan Proyek Pembangunan Saranan Dan Prasarana Tempat Pelelangan Ikan (TPI) Di Tuban Jawa Timur. Rang Teknik Journal, 5(1), 24–42. https://doi.org/10.31869/rtj.v5i1.2706

Widiasanti, I., & Lenggogeni. (2014). Manajemen Konstruksi. Bandung: PT Remaja Rosdakarya Offset.

Downloads

Published

2022-11-19

Issue

Section

Articles