Analisa risiko pembangunan dermaga untuk pembangkit listrik terapung (Barge Mounted Power Plant/BMPP) di Kolaka, Sulawesi Tenggara
DOI:
https://doi.org/10.22225/pd.14.2.13019.260-273Keywords:
BMPP, jetty, risk managementAbstract
Electricity utilization in the provinces of South Sulawesi, Southeast and West Sulawesi is rapidly growing at a high rate. In Southeast Sulawesi Province, between the years of 2020 and 2024, it significantly grew by 12.66% per year. To meet with this high demand, for such a reason, PT Perusahaan Listrik Negara Indonesia Power/Electricity State Owned Company Info (PLN) ordered Nusantara II Barge Mounted Power Plant (BMPP) to PT PAL Surabaya and built a new jetty to mount the 60 MW plant in Wolo, Kolaka, Southeast Sulawesi. It is important to conduct risk management to ensure the success of the project by identifying and mitigating impact the risks that could be an obstacle smoothing delivery of the BMPP and the construction of its mounting dock. This study aims to analyze and manage risks for the construction of the BMPP Jetty. A risk analysis of the project was made to oversee what risks could interfere during the procurement stage, delivery the plant, implementation/construction stage up to the completion of the project. The research in this paper uses a descriptive qualitative approach and survey to examine the consequences of risks collected based on purposive sampling from Users, Contractors, Project Owners, and Project workers. The identified risks are then calculated and mitigated as necessary to control them. There were 47 risks identified, and after thorough analysis using the HIRADC method, 17 (36%) risks were low, 29 (62%) risks were moderate and 1 (2%) risk was high risk, which was related to the delivery of the BMPP itself. This research can help users, project owners, or other stakeholders in identifying, understanding, and responding to risks more effectively so that projects can be completed on time, without work accidents, but good quality, and within the planned budget. Good risk control and mitigation have made the project completed on time without accidents, delays, and with good quality delivered. The pattern of project implementation and management are be able to serve as reference to similar project in the future.
References
Apriliyanti, I. D., Nugraha, D. B., Kristiansen, S., & Overland, I. (2024). To reform or not reform? Competing energy transition perspectives on Indonesia’s monopoly electricity supplier Perusahaan Listrik Negara (PLN). Energy Research & Social Science, 118, 103797. https://doi.org/https://doi.org/10.1016/j.erss.2024.103797
AS/NZS 4360. (2004). Risk Management Guidelines Companion to AS/NZS 4360:2004. Standards Australia/Standards New Zealand, 10(5), 31–31. https://globaltraining.edu.au/global_training_institute/Resource_Library/Australian_Standards/HB_436-2004_Guidelines_to_AS_NZS_4360-2004_Risk_Management_Guidelines_Companion_to_AS_NZS_4360-2004.pdf
Atma, H., Ruzzenenti, F., & van den Broek, M. A. (2025). Exploring the evolution of long-term electricity demand and load curves in emerging economies: A case study of Indonesia’s energy transition. Energy Strategy Reviews, 60(June), 101805. https://doi.org/10.1016/j.esr.2025.101805
Dewi, K. P., Kurniawan, J., Irawan, H., & Purba, H. H. (2022). Risks Identification In Construction Of Jetty Projects: Literature Review. Rekayasa Sipil, 11(2), 59. https://doi.org/10.22441/jrs.2022.v11.i2.02
Edi (PT PAL), R. (2025). PT PAL Indonesia Kebut Persiapan Performance Test BMPP Nusantara II , Dukung Persiapan Nataru. https://www.pal.co.id/pt-pal-indonesia-kebut-persiapan-performance-test-bmpp-nusantara-ii-dukung-persiapan-nataru-2025/
Ghaeb, O., & Mahjoob, A. M. R. (2023). Risk Response in Construction Project: A Review Study. Journal of Engineering, 29(08 SE-Articles), 121–137. https://doi.org/10.31026/j.eng.2023.08.09
Ismiyati, Sanggawuri, R., & Handajani, M. (2019). Penerapan Manajemen Resiko pada Pembangunan Proyek Perpanjangan Dermaga log (Studi Kasus: Pelabuhan DalamTanjung Emas Semarang). In Media Komunikasi Teknik Sipil (Vol. 25, Issue 2). https://doi.org/mkts.v25i2.19467
ISO 31000. (2018). ISO 31000:2018 Risk management-Guidelines. International Organization for Standardization, 2018.
ISO31073. (2022). International Standard Iso 31073. 2022. www.iso.org
Jayady, A., & Moerdianto, E. (2022). Risk Management of Time Control on the Construction of Saumlaki Port. Indonesian Journal of Multidisciplinary Science, 1(12), 1581–1597. https://doi.org/10.55324/ijoms.v1i12.239
Joubert, F. J., & Pretorius, L. (2020). Design and Construction Risks for a Shipping Port and Container Terminal: Case Study. Journal of Waterway, Port, Coastal, and Ocean Engineering, 146(1). https://doi.org/10.1061/(asce)ww.1943-5460.0000537
Kepmen ESDM No. 188.K, PT. Perusahaan Listrik Negara 1 (2025). https://web.pln.co.id/statics/uploads/2024/04/buku-ruptl-2025-2034.pdf
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and controlling. In John Wiley & Sons,.
Lou, J., Rader, A., Gultom, Y. M. L., Hilde, T. C., & Hultman, N. (2024). Navigating SDG 8 in the decarbonizing landscape of emerging economies: a case study of Indonesia. Sustainable Earth Reviews, 7(1). https://doi.org/10.1186/s42055-024-00096-5
Marais, E. A., Akker, O., & Wiedinmyer, C. (2022). Greenhouse gas and air pollutant emissions from power barges (powerships). Environmental Science: Advances, 1(2), 164–169. https://doi.org/10.1039/d1va00049g
Mulcahy, R. (2018). Rita Mulcahys PMP Exam Prep 9th Edition.pdf (p. 690). RMC Publications, Inc.
Nainggolan, H., & Hendra, H. (2023). Evaluasi Penerapan Sistem Manajemen Keselamatan Dan Kesehatan Kerja (K3) Pada Industri Galangan Kapal Kecil Di Indonesia. Jurnal Kesehatan Tambusai, 4(4), 7129–7151. https://doi.org/10.31004/jkt.v4i4.16083
Nindya, K., & Padma, I. (2024). Pekerjaan Engineering Procurement Construction (EPC) Infrastruktur BMPP di Wolo - Kolaka.
Pamik, M., Bayraktar, M., Konur, O., & Nuran, M. (2022). A Revelatory Case Study for the Emergence of Powerships: The Floating Power Plant Innovation for Rural Electrification. Transactions on Maritime Science, 11(1), 54–66. https://doi.org/10.7225/toms.v11.n01.w10
PMI. (2017). PMBOK® GUIDE, SIXTH Ed. (6th Editio). PMI.org (PMI U.
PMI. (2021). PMBOK® GUIDE, 7th Ed. A Guide to the Project Management Body of Knowledge (7TH Editio, Issue July). PMI.org (PMI USA).
Putro, G. P. (2006). Manajemen Risiko. In Dep. K3 FKMUI.
Salim, M. A., & Siswanto, A. B. (2022). Manajemen Risiko K3 Konstruksi. In Kementerian Pekerjaan Umum dan Perumahan Rakyat (Issue January). https://simantu.pu.go.id/epel/edok/9b7dd_Bahan_Tayang_Manajemen_Resiko_K3.pdf
Santosa, J., Kuncoro, A. H., Dwijatmiko, A., Hesty, N. W., & Darmawan, A. (2023). The Role of Nuclear Power Plants in Indonesia towards Net Zero Emissions (NZE) in 2060 with a Multi Regions Approach. Evergreen, 10(3), 1660–1673. https://doi.org/10.5109/7151715
Sarjiya, Putranto, L. M., Tumiran, Budi, R. F. S., Novitasari, D., & Deendarlianto. (2023). Generation expansion planning with a renewable energy target and interconnection option: A case study of the Sulawesi region, Indonesia. Renewable and Sustainable Energy Reviews, 183, 113489. https://doi.org/https://doi.org/10.1016/j.rser.2023.113489
Sharma, S., & Gupta, A. K. (2019). Risk Identification and Management in Construction Projects: Literature Review. International Journal of Humanities, Arts and Social Sciences, 5(6), 224–231. https://doi.org/10.20469/ijhss.5.20002-6
Sutopo, T., Pandjaitan, M. M. L. W., & Lukas. (2025). BMPP Metode Percepatan Waktu Pekerjaan Pemancangan Infrastruktur Barge Mounting Power Plan (BMMP) Di Wolo - Kolaka. Jurnal Praktik Keinsinyuran, 1(03), 243–248. https://doi.org/10.25170/jpk.v1i03.6334
Triliantanto, D. A. (2020). Metodologi Penelitian, Panduan Lengkap Penelitian dengan Mudah (Giovani (ed.); Pertama). Penerbit Andi.
Winarno, Priadi, A. A., & Wulandari, R. S. (2024). Shipbuilding Risk Assessment: Legal Frameworks and Practical Challenges in Indonesian Shipyards. International Journal of Safety and Security Engineering, 14(4), 1061–1072. https://doi.org/10.18280/ijsse.140405
Windapo, A., Salie, M., & Umeokafor, N. (2023). The Efficacy of Innovative Project Management Tools in Mitigating Risks and Uncertainty in the Project Delivery Process. E3S Web of Conferences, 409. https://doi.org/10.1051/e3sconf/202340906017
Yosaka, A. R., & Basuki, M. (2022). Analisa Risiko Pembangunan Barge Mounted Power Plant (Bmpp) 60 Mw Di Pt. Pal Indonesia (Persero) Menggunakan Metode Failure Mode and Effect Analysis (Fmea) Dan Matrik Risiko. Jurnal Sumberdaya Bumi Berkelanjutan (SEMITAN), 1(1), 476–492. https://doi.org/10.31284/j.semitan.2022.3197
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Yani Esbe, Savitri Citra Budi, Irawadi Prihaswan

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
1. Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International (CC BY-SA 4.0) that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
2. Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
3. Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).